WIN. 14-35 MOTT AVENUE. GREENPORT II - SOUTH

1403 GATEWAY BOULEVARD (Boro: 4, Block: 15574, Lot: 36)
Queens

Duration

Total Duration:2.7 years
Start Date:Nov 2018
End Date:Jul 2021

Identifiers

Project ID:67287
Building ID:999557
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20182019202020212022202320242025ActualOfficial
WIN. 14-35 MOTT AVENUE. GREENPOR...1403 GATEWAY BOULEVARD(Boro: 4, Block: 15574, Lot: 36)Queens2.7yrs2.1yrs

Timeline Events (4)

Nov 08, 2018
Earliest DOB Filing
Jun 28, 2019
Project Start (HPD)
Jul 29, 2021
Building Completion (HPD)
Jul 29, 2021
Certificate of Occupancy