LOGAN FOUNTAIN
265 LOGAN STREET (Boro: 3, Block: 4154, Lot: 7501)
Brooklyn
Duration
Total Duration:6.5 years
Start Date:Sep 2018
End Date:Mar 2025
Identifiers
Project ID:66904
Building ID:999393
Data Quality Note
19-36 (Fair)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (8)
Sep 17, 2018
Earliest DOB Filing
Dec 01, 2018
Hpd Construction Financing + Funding Programs [NO_ZAP_21DHS031K] Earliest EAS Work (Phase I ESA, Asbestos Inspection, Soil Testing)
Mar 31, 2022
Hpd Construction Financing + Funding Programs [NO_ZAP_21DHS031K] Lead Agency Letter
Mar 31, 2022
Hpd Construction Financing + Funding Programs [NO_ZAP_21DHS031K] EAS Date
Mar 31, 2022
✅ Hpd Construction Financing + Funding Programs [NO_ZAP_21DHS031K] Negative Declaration
Jun 16, 2022
HPD Financing ("Project Start")
Nov 23, 2022
Fully Permitted
Mar 20, 2025
Certificate of Occupancy