TYPE A. 1490 SOUTHERN BLVD. MWBE RFP SITE E

1490 SOUTHERN BOULEVARD (Boro: 2, Block: 2981, Lot: 14)
Bronx

Duration

Total Duration:4.9 years
Start Date:Jan 2016
End Date:Dec 2020

Identifiers

Project ID:63877
Building ID:997082

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2016201720182019202020212022202320242025ActualOfficialTYPE A. 1490 SOUTHERN BLVD. MWBE...1490 SOUTHERN BOULEVARD(Boro: 2, Block: 2981, Lot: 14)Bronx4.9yrs2.0yrs

Timeline Events (9)

Jan 29, 2016
Udaap Designation + Hpd Construction Financing (Contemplated) [P2017X0271] Earliest EAS Work (Site Survey)
Oct 31, 2017
Udaap Designation + Hpd Construction Financing (Contemplated) [P2017X0271] Lead Agency Letter
Dec 20, 2017
Udaap Designation + Hpd Construction Financing (Contemplated) [P2017X0271] EAS Date
Dec 21, 2017
Earliest DOB Filing
Dec 21, 2017
✅ Udaap Designation + Hpd Construction Financing (Contemplated) [P2017X0271] Negative Declaration
Dec 26, 2018
HPD Financing ("Project Start")
Mar 13, 2019
Fully Permitted
Dec 18, 2020
Certificate of Occupancy
Dec 18, 2020
Building Completion (HPD)