HELP. 771-775 CROTONA PARK NORTH
775 CROTONA PARK NORTH (Boro: 2, Block: 2952, Lot: 7501)
Bronx
Duration
Total Duration:4.2 years
Start Date:Sep 2016
End Date:Dec 2020
Identifiers
Project ID:61740
Building ID:996806
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Sep 21, 2016
Hpd Construction Financing [NO_ZAP_17HPD041X] Earliest EAS Work (Noise Monitoring)
Dec 19, 2016
Earliest DOB Filing
Jan 10, 2017
Hpd Construction Financing [NO_ZAP_17HPD041X] Lead Agency Letter
Apr 28, 2017
Hpd Construction Financing [NO_ZAP_17HPD041X] EAS Date
May 31, 2017
✅ Hpd Construction Financing [NO_ZAP_17HPD041X] Negative Declaration
Nov 15, 2017
HPD Financing ("Project Start")
Jul 10, 2018
Fully Permitted
Dec 16, 2020
Certificate of Occupancy
Dec 16, 2020
Building Completion (HPD)