CUCS. 711 EAST 211TH ST AND 718 EAST 212TH ST.

718 EAST 212 STREET (Boro: 2, Block: 4657, Lot: 71)
Bronx

Duration

Total Duration:5.5 years
Start Date:Aug 2017
End Date:Feb 2023

Identifiers

Project ID:68125
Building ID:996758

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201720182019202020212022202320242025ActualOfficialCUCS. 711 EAST 211TH ST AND 718 ...718 EAST 212 STREET(Boro: 2, Block: 4657, Lot: 71)Bronx5.5yrs2.1yrs

Timeline Events (9)

Aug 01, 2017
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_20HPD010X] Earliest EAS Work (Phase I ESA)
Nov 08, 2018
Earliest DOB Filing
Oct 07, 2019
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_20HPD010X] Lead Agency Letter
Oct 07, 2020
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_20HPD010X] EAS Date
Oct 13, 2020
✅ Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_20HPD010X] Negative Declaration
Dec 17, 2020
HPD Financing ("Project Start")
Mar 04, 2021
Fully Permitted
Feb 02, 2023
Building Completion (HPD)
Feb 02, 2023
Certificate of Occupancy