BED STUY CENTRAL AND NORTH PHASE I
1835 ATLANTIC AVENUE (Boro: 3, Block: 1710, Lot: 51)
Brooklyn
Duration
Total Duration:22.2 years
Start Date:Jan 2003
End Date:Mar 2025
Identifiers
Project ID:65315
Building ID:996114
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (11)
Jan 08, 2003
Urban Renewal Plan Amendment + Disposition City Owned Property + Zoning Map Amendment [P2003K0259] EAS Date
Jan 09, 2003
Urban Renewal Plan Amendment + Disposition City Owned Property + Zoning Map Amendment [P2003K0259] Lead Agency Letter
Jan 09, 2003
✅ Urban Renewal Plan Amendment + Disposition City Owned Property + Zoning Map Amendment [P2003K0259] Negative Declaration
Nov 27, 2017
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Earliest EAS Work (Phase I ESA)
Mar 06, 2019
Earliest DOB Filing
Feb 24, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] EAS Date
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Negative Declaration
Jun 30, 2021
HPD Financing ("Project Start")
Mar 01, 2022
Fully Permitted
Mar 25, 2025
Certificate of Occupancy
Mar 25, 2025
Building Completion (HPD)