NME III
304 WEST 150 STREET (Boro: 1, Block: 2045, Lot: 98)
Manhattan
Duration
Total Duration:6.1 years
Start Date:Mar 2019
End Date:Apr 2025
Identifiers
Project ID:64689
Building ID:994121
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (6)
Mar 26, 2019
✅ Udaap Designation + Disposition City Owned Property + Acquisition City Property [P2017M0377] Negative Declaration
Aug 13, 2019
Earliest DOB Filing
Dec 22, 2021
HPD Financing ("Project Start")
Mar 17, 2022
Fully Permitted
Apr 29, 2025
Building Completion (HPD)
Apr 29, 2025
Certificate of Occupancy