DOE. 555 NEREID AVE. MULLER

555 NEREID AVENUE (Boro: 2, Block: 5065, Lot: 1)
Bronx

Duration

Total Duration:9.2 years
Start Date:Apr 2012
End Date:Jul 2021

Identifiers

Project ID:61271
Building ID:99387
Data Quality Note
0-18 (Poor)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2012201420162018202020222024ActualOfficial
DOE. 555 NEREID AVE. MULLER555 NEREID AVENUE(Boro: 2, Block: 5065, Lot: 1)Bronx9.2yrs2.3yrs

Timeline Events (10)

Apr 18, 2012
Other Discretionary Permit [NO_ZAP_12DHS012X] Earliest EAS Work (Noise Monitoring)
Nov 01, 2012
Other Discretionary Permit [NO_ZAP_12DHS012X] EAS Date
Dec 27, 2012
Other Discretionary Permit [NO_ZAP_12DHS012X] Lead Agency Letter
Dec 27, 2012
✅ Other Discretionary Permit [NO_ZAP_12DHS012X] Negative Declaration
Sep 01, 2014
Variance Use + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA139X] Earliest EAS Work (Phase I Environmental Site Assessment)
Jun 15, 2017
Variance Use + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA139X] Lead Agency Letter
Apr 17, 2018
Variance Use + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA139X] EAS Date
Apr 17, 2018
✅ Variance Use + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA139X] Negative Declaration
Mar 28, 2019
HPD Financing ("Project Start")
Jul 09, 2021
Building Completion (HPD)