Duration

Total Duration:5.8 years
Start Date:Jan 2017
End Date:Oct 2022

Identifiers

Project ID:63933
Building ID:992262

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201720182019202020212022202320242025ActualOfficialSUS. 461 ALABAMA AVENUE. MWBE SI...461 ALABAMA AVENUE(Boro: 3, Block: 3803, Lot: 6)Brooklyn5.8yrs2.2yrs

Timeline Events (9)

Jan 01, 2017
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017K0286] Earliest EAS Work (Phase I ESA)
May 18, 2018
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017K0286] EAS Date
Jun 20, 2018
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017K0286] Lead Agency Letter
Jul 02, 2018
✅ Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017K0286] Negative Declaration
Apr 15, 2019
Earliest DOB Filing
Jul 31, 2020
HPD Financing ("Project Start")
Sep 10, 2020
Fully Permitted
Oct 28, 2022
Building Completion (HPD)
Oct 28, 2022
Certificate of Occupancy