EBENEZER PLAZA PHASE II

589 CHRISTOPHER AVENUE (Boro: 3, Block: 3861, Lot: 1)
Brooklyn

Duration

Total Duration:9.6 years
Start Date:Nov 2015
End Date:Jun 2025

Identifiers

Project ID:63776
Building ID:991993

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficialEBENEZER PLAZA PHASE II589 CHRISTOPHER AVENUE(Boro: 3, Block: 3861, Lot: 1)Brooklyn9.6yrs3.0yrs

Timeline Events (9)

Nov 03, 2015
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] Earliest EAS Work (Phase I ESA)
Sep 01, 2017
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] Lead Agency Letter
Sep 01, 2017
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] EAS Date
Sep 01, 2017
✅ Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] Negative Declaration
Sep 09, 2019
Earliest DOB Filing
Jun 29, 2022
HPD Financing ("Project Start")
Jul 12, 2022
Fully Permitted
Jun 13, 2025
Building Completion (HPD)
Jun 13, 2025
Certificate of Occupancy