HUNTERS POINT SOUTH PARCELS F AND G

57-28 2 STREET (Boro: 4, Block: 6, Lot: 7503)
Queens

Duration

Total Duration:15.0 years
Start Date:Apr 2007
End Date:Mar 2022

RFP Information

Hunter's Point South Parcels F and G RFP

Identifiers

Project ID:66970
Building ID:991747

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2007200920112013201520172019202120232025ActualOfficialHUNTERS POINT SOUTH PARCELS F AN...57-28 2 STREET(Boro: 4, Block: 6, Lot: 7503)Queens15.0yrs2.3yrs

Timeline Events (15)

Apr 11, 2007
Zoning Map Amendment + Zoning Text Amendment (Contemplated) + City Map Amendment + Acquisition City Property (Contemplated) + Site Selection Public Facility + Disposition City Owned Property [NO_ZAP_07DME023Q] Lead Agency Letter
Oct 05, 2007
Zoning Map Amendment + City Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment [P2008Q0279] EAS Date
Oct 12, 2007
Zoning Map Amendment + City Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment [P2008Q0279] Lead Agency Letter
Oct 12, 2007
⚠️ Zoning Map Amendment + City Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment [P2008Q0279] Positive Declaration (EIS Required)
Jun 02, 2016
RFP Release: Hunter's Point South Parcels F and G RFP
Nov 17, 2017
✅ RFP Designation: Hunter's Point South Parcels F and G RFP
Apr 01, 2018
Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing [NO_ZAP_19HPD010Q] Earliest EAS Work (Phase I ESA)
Mar 08, 2019
Earliest DOB Filing
Aug 16, 2019
Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing [NO_ZAP_19HPD010Q] Lead Agency Letter
Aug 16, 2019
Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing [NO_ZAP_19HPD010Q] EAS Date
Sep 04, 2019
✅ Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing [NO_ZAP_19HPD010Q] Negative Declaration
Dec 20, 2019
HPD Financing ("Project Start")
Jan 14, 2020
Fully Permitted
Mar 29, 2022
Building Completion (HPD)
Mar 29, 2022
Certificate of Occupancy