EXCELSIOR II

126 WEST 169 STREET (Boro: 2, Block: 2518, Lot: 31)
Bronx

Duration

Total Duration:17.8 years
Start Date:May 2001
End Date:Feb 2019

Identifiers

Project ID:52119
Building ID:990448
Data Quality Note
0-18 (Poor)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2001200520092013201720212025ActualOfficial
EXCELSIOR II126 WEST 169 STREET(Boro: 2, Block: 2518, Lot: 31)Bronx17.8yrs3.2yrs

Timeline Events (8)

May 16, 2001
Earliest DOB Filing
Feb 12, 2003
Fully Permitted
Dec 03, 2013
Hpd Construction Financing + Udaap Designation [NO_ZAP_15HPD040X] Earliest EAS Work (Phase I ESA)
Jan 28, 2015
Hpd Construction Financing + Udaap Designation [NO_ZAP_15HPD040X] Lead Agency Letter
Apr 07, 2015
Hpd Construction Financing + Udaap Designation [NO_ZAP_15HPD040X] EAS Date
Apr 07, 2015
✅ Hpd Construction Financing + Udaap Designation [NO_ZAP_15HPD040X] Negative Declaration
Nov 25, 2015
HPD Financing ("Project Start")
Feb 14, 2019
Building Completion (HPD)