Duration
Total Duration:5.0 years
Start Date:Oct 2019
End Date:Oct 2024
Identifiers
Project ID:64828
Building ID:989272
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Oct 03, 2019
Earliest DOB Filing
Dec 04, 2019
Hpd Construction Financing [NO_ZAP_20HPD003K] Lead Agency Letter
Dec 06, 2019
Hpd Construction Financing [NO_ZAP_20HPD003K] Earliest EAS Work (Phase I ESA)
Jun 17, 2020
Hpd Construction Financing [NO_ZAP_20HPD003K] EAS Date
Aug 10, 2020
✅ Hpd Construction Financing [NO_ZAP_20HPD003K] Negative Declaration
Sep 19, 2022
HPD Financing ("Project Start")
Mar 07, 2023
Fully Permitted
Oct 11, 2024
Building Completion (HPD)
Oct 11, 2024
Certificate of Occupancy