PROJECT HOSPITALITY. 221 PORT RICHMOND AVE

1540 CASTLETON AVENUE (Boro: 5, Block: 1035, Lot: 12)
Staten Island

Duration

Total Duration:4.3 years
Start Date:Jul 2018
End Date:Oct 2022

Identifiers

Project ID:67494
Building ID:989187

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20182019202020212022202320242025ActualOfficialPROJECT HOSPITALITY. 221 PORT RI...1540 CASTLETON AVENUE(Boro: 5, Block: 1035, Lot: 12)Staten Island4.3yrs3.0yrs

Timeline Events (9)

Jul 02, 2018
Hpd Construction Financing [NO_ZAP_19HPD034R] Earliest EAS Work (Phase I ESA)
Nov 08, 2018
Earliest DOB Filing
Feb 27, 2019
Hpd Construction Financing [NO_ZAP_19HPD034R] Lead Agency Letter
Apr 29, 2019
Hpd Construction Financing [NO_ZAP_19HPD034R] EAS Date
May 01, 2019
✅ Hpd Construction Financing [NO_ZAP_19HPD034R] Negative Declaration
Nov 04, 2019
HPD Financing ("Project Start")
Jun 05, 2020
Fully Permitted
Oct 31, 2022
Building Completion (HPD)
Oct 31, 2022
Certificate of Occupancy