COMPASS 6

1923 WEST FARMS ROAD (Boro: 2, Block: 3016, Lot: 7503)
Bronx

Duration

Total Duration:13.3 years
Start Date:Jan 2010
End Date:May 2023

Identifiers

Project ID:66879
Building ID:989183

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20102012201420162018202020222024ActualOfficialCOMPASS 61923 WEST FARMS ROAD(Boro: 2, Block: 3016, Lot: 7503)Bronx13.3yrs2.4yrs

Timeline Events (13)

Jan 13, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property [P2010X0193] EAS Date
Jan 13, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Hpd Hdc Program Funding (Contemplated) [P2011X0142] EAS Date
Jan 13, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Hpd Hdc Program Funding (Contemplated) [P2011X0180] EAS Date
Jan 25, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property [P2010X0193] Lead Agency Letter
Jan 25, 2010
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property [P2010X0193] Positive Declaration (EIS Required)
Jan 25, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Hpd Hdc Program Funding (Contemplated) [P2011X0142] Lead Agency Letter
Jan 25, 2010
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Hpd Hdc Program Funding (Contemplated) [P2011X0142] Positive Declaration (EIS Required)
Jan 25, 2010
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Hpd Hdc Program Funding (Contemplated) [P2011X0180] Positive Declaration (EIS Required)
Jul 03, 2018
Earliest DOB Filing
Dec 17, 2020
HPD Financing ("Project Start")
Dec 29, 2020
Fully Permitted
May 11, 2023
Building Completion (HPD)
May 11, 2023
Certificate of Occupancy