LINDEN TERRACE BUILDING 2
573 EMERALD STREET (Boro: 3, Block: 4496, Lot: 15)
Brooklyn
Duration
Total Duration:5.9 years
Start Date:Jun 2017
End Date:May 2023
Identifiers
Project ID:65304
Building ID:989116
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (8)
Jun 16, 2017
Zoning Map Amendment + Zoning Text Amendment [P2016K0159] EAS Date
Jun 19, 2017
Zoning Map Amendment + Zoning Text Amendment [P2016K0159] Lead Agency Letter
Jun 19, 2017
✅ Zoning Map Amendment + Zoning Text Amendment [P2016K0159] Negative Declaration
Jan 29, 2019
Earliest DOB Filing
Dec 17, 2020
HPD Financing ("Project Start")
May 18, 2021
Fully Permitted
May 25, 2023
Building Completion (HPD)
May 25, 2023
Certificate of Occupancy