SPOFFORD DETENTION CENTER PHASE 1
720 TIFFANY STREET (Boro: 2, Block: 2738, Lot: 7501)
Bronx
Duration
Total Duration:6.0 years
Start Date:Jun 2016
End Date:Jun 2022
Identifiers
Project ID:63151
Building ID:988458
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Jun 01, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] Earliest EAS Work (Phase I ESA)
Apr 20, 2017
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] Lead Agency Letter
May 23, 2017
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] EAS Date
May 23, 2017
⚠️ Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] Positive Declaration (EIS Required)
Jul 03, 2018
Earliest DOB Filing
Jun 27, 2019
HPD Financing ("Project Start")
Aug 20, 2019
Fully Permitted
Jun 09, 2022
Building Completion (HPD)
Jun 09, 2022
Certificate of Occupancy