WSFSSH. 145 WEST 108TH ST. VALLEY LODGE

137 WEST 108 STREET (Boro: 1, Block: 1863, Lot: 7501)
Manhattan

Duration

Total Duration:15.5 years
Start Date:Mar 2006
End Date:Sep 2021

RFP Information

NYC Supportive Housing RFQ

Identifiers

Project ID:44256
Building ID:988143

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2006200820102012201420162018202020222024ActualOfficialWSFSSH. 145 WEST 108TH ST. VALLE...137 WEST 108 STREET(Boro: 1, Block: 1863, Lot: 7501)Manhattan15.5yrs2.7yrs

Timeline Events (15)

Mar 28, 2006
Disposition City Owned Property + Udaap Designation + Housing Plan Project [P2008M0056] Earliest EAS Work (Environmental Assessment Statement Preparation)
Apr 28, 2006
Disposition City Owned Property + Udaap Designation + Housing Plan Project [P2008M0056] Lead Agency Letter
Jul 11, 2006
Disposition City Owned Property + Udaap Designation + Housing Plan Project [P2008M0056] EAS Date
Jul 14, 2006
✅ Disposition City Owned Property + Udaap Designation + Housing Plan Project [P2008M0056] Negative Declaration
Jun 25, 2013
RFP Release: NYC Supportive Housing RFQ
Mar 19, 2014
✅ RFP Designation: NYC Supportive Housing RFQ
Jun 01, 2015
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0488] Earliest EAS Work (Phase I ESA)
May 23, 2017
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0488] Lead Agency Letter
May 23, 2017
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0488] EAS Date
May 23, 2017
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0488] Positive Declaration (EIS Required)
Oct 13, 2017
Earliest DOB Filing
Dec 31, 2018
HPD Financing ("Project Start")
May 15, 2019
Fully Permitted
Sep 29, 2021
Building Completion (HPD)
Sep 29, 2021
Certificate of Occupancy