BEDFORD UNION ARMORY

1089 PRESIDENT STREET (Boro: 3, Block: 1274, Lot: 7501)
Brooklyn

Duration

Total Duration:6.8 years
Start Date:Aug 2016
End Date:Jun 2023

Identifiers

Project ID:65291
Building ID:988140
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2016201720182019202020212022202320242025ActualOfficial
BEDFORD UNION ARMORY1089 PRESIDENT STREET(Boro: 3, Block: 1274, Lot: 7501)Brooklyn6.8yrs4.4yrs

Timeline Events (9)

Aug 26, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2016K0272] Earliest EAS Work (Transportation Demand Factors Analysis)
Dec 01, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2016K0272] Lead Agency Letter
Dec 23, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2016K0272] EAS Date
Dec 23, 2016
⚠️ Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2016K0272] Positive Declaration (EIS Required)
Jun 14, 2018
Earliest DOB Filing
Jan 31, 2019
HPD Financing ("Project Start")
Nov 14, 2019
Fully Permitted
Dec 29, 2021
Certificate of Occupancy
Jun 27, 2023
Building Completion (HPD)