CATON FLATS

800 FLATBUSH AVENUE (Boro: 3, Block: 5063, Lot: 7501)
Brooklyn

Duration

Total Duration:8.4 years
Start Date:Apr 2015
End Date:Aug 2023

Identifiers

Project ID:62109
Building ID:987706

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficialCATON FLATS800 FLATBUSH AVENUE(Boro: 3, Block: 5063, Lot: 7501)Brooklyn8.4yrs4.6yrs

Timeline Events (9)

Apr 01, 2015
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0157] Earliest EAS Work (Phase I ESA)
Oct 21, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0157] Lead Agency Letter
Oct 27, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0157] EAS Date
Oct 27, 2016
✅ Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0157] Negative Declaration
Aug 28, 2017
Earliest DOB Filing
Dec 26, 2018
HPD Financing ("Project Start")
May 29, 2019
Fully Permitted
May 19, 2021
Certificate of Occupancy
Aug 18, 2023
Building Completion (HPD)