RISEBORO. 37 HILLSIDE AVENUE

37 HILLSIDE AVENUE (Boro: 1, Block: 2170, Lot: 118)
Manhattan

Duration

Total Duration:13.6 years
Start Date:Apr 2010
End Date:Dec 2023

Identifiers

Project ID:67720
Building ID:986618

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20102012201420162018202020222024ActualOfficialRISEBORO. 37 HILLSIDE AVENUE37 HILLSIDE AVENUE(Boro: 1, Block: 2170, Lot: 118)Manhattan13.6yrs3.3yrs

Timeline Events (10)

Apr 30, 2010
Variance Bulk [NO_ZAP_09BSA027M] Lead Agency Letter
Jun 21, 2018
Hpd Construction Financing [NO_ZAP_19HPD071M] Earliest EAS Work (Noise Monitoring)
Jun 07, 2019
Earliest DOB Filing
Jun 10, 2019
Hpd Construction Financing [NO_ZAP_19HPD071M] Lead Agency Letter
Apr 22, 2020
Hpd Construction Financing [NO_ZAP_19HPD071M] EAS Date
May 15, 2020
✅ Hpd Construction Financing [NO_ZAP_19HPD071M] Negative Declaration
Aug 20, 2020
HPD Financing ("Project Start")
Feb 25, 2021
Fully Permitted
Dec 12, 2023
Building Completion (HPD)
Dec 12, 2023
Certificate of Occupancy