FOXY.2016 ARTHUR AVENUE
612 EAST 179 STREET (Boro: 2, Block: 3068, Lot: 69)
Bronx
Duration
Total Duration:4.0 years
Start Date:Jun 2017
End Date:Jun 2021
Identifiers
Project ID:66651
Building ID:986550
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Jun 16, 2017
Hpd Construction Financing [NO_ZAP_19HPD035X] Earliest EAS Work (Phase I ESA)
Aug 17, 2018
Earliest DOB Filing
Oct 15, 2018
Hpd Construction Financing [NO_ZAP_19HPD035X] Lead Agency Letter
Nov 13, 2018
Hpd Construction Financing [NO_ZAP_19HPD035X] EAS Date
Nov 13, 2018
✅ Hpd Construction Financing [NO_ZAP_19HPD035X] Negative Declaration
Dec 20, 2018
HPD Financing ("Project Start")
Jun 04, 2019
Fully Permitted
Jun 29, 2021
Building Completion (HPD)
Jun 29, 2021
Certificate of Occupancy