FOXY.2016 ARTHUR AVENUE

612 EAST 179 STREET (Boro: 2, Block: 3068, Lot: 69)
Bronx

Duration

Total Duration:4.0 years
Start Date:Jun 2017
End Date:Jun 2021

Identifiers

Project ID:66651
Building ID:986550

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201720182019202020212022202320242025ActualOfficialFOXY.2016 ARTHUR AVENUE612 EAST 179 STREET(Boro: 2, Block: 3068, Lot: 69)Bronx4.0yrs2.5yrs

Timeline Events (9)

Jun 16, 2017
Hpd Construction Financing [NO_ZAP_19HPD035X] Earliest EAS Work (Phase I ESA)
Aug 17, 2018
Earliest DOB Filing
Oct 15, 2018
Hpd Construction Financing [NO_ZAP_19HPD035X] Lead Agency Letter
Nov 13, 2018
Hpd Construction Financing [NO_ZAP_19HPD035X] EAS Date
Nov 13, 2018
✅ Hpd Construction Financing [NO_ZAP_19HPD035X] Negative Declaration
Dec 20, 2018
HPD Financing ("Project Start")
Jun 04, 2019
Fully Permitted
Jun 29, 2021
Building Completion (HPD)
Jun 29, 2021
Certificate of Occupancy