50 PENN

62 PENNSYLVANIA AVENUE (Boro: 3, Block: 3669, Lot: 7501)
Brooklyn

Duration

Total Duration:3.8 years
Start Date:Feb 2018
End Date:Dec 2021

Identifiers

Project ID:66858
Building ID:986253

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20182019202020212022202320242025ActualOfficial50 PENN62 PENNSYLVANIA AVENUE(Boro: 3, Block: 3669, Lot: 7501)Brooklyn3.8yrs2.6yrs

Timeline Events (9)

Feb 09, 2018
Hpd Construction Financing [NO_ZAP_19HPD017K] Earliest EAS Work (Phase I ESA)
Jul 30, 2018
Earliest DOB Filing
Nov 08, 2018
Hpd Construction Financing [NO_ZAP_19HPD017K] Lead Agency Letter
Mar 15, 2019
Hpd Construction Financing [NO_ZAP_19HPD017K] EAS Date
Mar 25, 2019
✅ Hpd Construction Financing [NO_ZAP_19HPD017K] Negative Declaration
Apr 26, 2019
HPD Financing ("Project Start")
Oct 16, 2019
Fully Permitted
Dec 14, 2021
Building Completion (HPD)
Dec 14, 2021
Certificate of Occupancy