WSFSSH. 275 EAST138TH ST. TRES PUENTES
295 EAST 138 STREET (Boro: 2, Block: 2314, Lot: 15)
Bronx
Duration
Total Duration:4.3 years
Start Date:Aug 2014
End Date:Dec 2018
Identifiers
Project ID:57668
Building ID:985850
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Aug 27, 2014
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Authorization [P2014X0051] Earliest EAS Work (Site Survey)
Mar 13, 2015
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Authorization [P2014X0051] Lead Agency Letter
Apr 13, 2015
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Authorization [P2014X0051] EAS Date
Apr 20, 2015
✅ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Authorization [P2014X0051] Negative Declaration
Jun 09, 2015
Earliest DOB Filing
May 19, 2016
HPD Financing ("Project Start")
Jan 31, 2017
Fully Permitted
Dec 31, 2018
Certificate of Occupancy
Dec 31, 2018
Building Completion (HPD)