J2
147-05 94 AVENUE (Boro: 4, Block: 9998, Lot: 42)
Queens
Duration
Total Duration:6.6 years
Start Date:Aug 2015
End Date:Apr 2022
Identifiers
Project ID:66720
Building ID:985837
Data Quality Note
0-18 (Poor)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (7)
Aug 21, 2015
Earliest DOB Filing
Oct 10, 2017
Hpd Construction Financing [NO_ZAP_18HPD063Q] Earliest EAS Work (Phase I ESA)
Sep 18, 2018
Hpd Construction Financing [NO_ZAP_18HPD063Q] EAS Date
Sep 30, 2019
Hpd Construction Financing [NO_ZAP_18HPD063Q] Lead Agency Letter
Sep 30, 2019
✅ Hpd Construction Financing [NO_ZAP_18HPD063Q] Negative Declaration
Dec 24, 2019
HPD Financing ("Project Start")
Apr 04, 2022
Building Completion (HPD)