SPRING CREEK PHASE 4B-2
389 SCHROEDERS AVENUE (Boro: 3, Block: 4452, Lot: 225)
Brooklyn
Duration
Total Duration:14.0 years
Start Date:Feb 2007
End Date:Feb 2021
Identifiers
Project ID:53680
Building ID:985794
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (6)
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Housing Plan Project [P2009K0050] Positive Declaration (EIS Required)
Aug 11, 2017
Earliest DOB Filing
Apr 18, 2019
HPD Financing ("Project Start")
Jul 24, 2019
Fully Permitted
Jan 27, 2021
Certificate of Occupancy
Feb 19, 2021
Building Completion (HPD)