IMPACCT. 811-817 LEXINGTON AVENUE

811 LEXINGTON AVENUE (Boro: 3, Block: 1622, Lot: 7502)
Brooklyn

Duration

Total Duration:6.4 years
Start Date:Nov 2017
End Date:Mar 2024

Identifiers

Project ID:67125
Building ID:985619

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201720182019202020212022202320242025ActualOfficialIMPACCT. 811-817 LEXINGTON AVENU...811 LEXINGTON AVENUE(Boro: 3, Block: 1622, Lot: 7502)Brooklyn6.4yrs2.9yrs

Timeline Events (9)

Nov 01, 2017
Hpd Construction Financing [NO_ZAP_18HPD091K] Earliest EAS Work (Phase I ESA)
Nov 21, 2018
Earliest DOB Filing
Oct 15, 2020
Hpd Construction Financing [NO_ZAP_18HPD091K] EAS Date
Oct 28, 2020
Hpd Construction Financing [NO_ZAP_18HPD091K] Lead Agency Letter
Mar 26, 2021
✅ Hpd Construction Financing [NO_ZAP_18HPD091K] Negative Declaration
May 11, 2021
HPD Financing ("Project Start")
Sep 10, 2021
Fully Permitted
Mar 19, 2024
Building Completion (HPD)
Mar 19, 2024
Certificate of Occupancy