SPRING CREEK PHASE 4B-2
498 SCHROEDERS AVENUE (Boro: 3, Block: 4452, Lot: 417)
Brooklyn
Duration
Total Duration:14.6 years
Start Date:Feb 2007
End Date:Oct 2021
Identifiers
Project ID:53680
Building ID:985164
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (6)
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Housing Plan Project [P2009K0050] Positive Declaration (EIS Required)
Aug 15, 2017
Earliest DOB Filing
Apr 18, 2019
HPD Financing ("Project Start")
Dec 10, 2019
Fully Permitted
Apr 06, 2021
Certificate of Occupancy
Oct 06, 2021
Building Completion (HPD)