Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (6)
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Housing Plan Project [P2009K0050] Positive Declaration (EIS Required)
Aug 22, 2017
Earliest DOB Filing
Apr 18, 2019
HPD Financing ("Project Start")
Oct 24, 2019
Fully Permitted
Jun 08, 2021
Certificate of Occupancy
Nov 22, 2021
Building Completion (HPD)