Duration

Total Duration:14.9 years
Start Date:Feb 2007
End Date:Dec 2021

Identifiers

Project ID:53680
Building ID:985157
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2007200920112013201520172019202120232025ActualOfficial
SPRING CREEK PHASE 4B-21123 ASHFORD STREET(Boro: 3, Block: 4452, Lot: 464)Brooklyn14.9yrs2.7yrs

Timeline Events (6)

Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Housing Plan Project [P2009K0050] Positive Declaration (EIS Required)
Aug 14, 2017
Earliest DOB Filing
Apr 18, 2019
HPD Financing ("Project Start")
Oct 21, 2019
Fully Permitted
Jun 09, 2021
Certificate of Occupancy
Dec 22, 2021
Building Completion (HPD)