SPRING CREEK PHASE 4B-2

392 SCHROEDERS AVENUE (Boro: 3, Block: 4452, Lot: 157)
Brooklyn

Duration

Total Duration:14.1 years
Start Date:Feb 2007
End Date:Mar 2021

Identifiers

Project ID:53680
Building ID:985152

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2007200920112013201520172019202120232025ActualOfficialSPRING CREEK PHASE 4B-2392 SCHROEDERS AVENUE(Boro: 3, Block: 4452, Lot: 157)Brooklyn14.1yrs1.9yrs

Timeline Events (6)

Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc [P2009K0050] Positive Declaration (EIS Required)
Aug 11, 2017
Earliest DOB Filing
Apr 18, 2019
HPD Financing ("Project Start")
Aug 13, 2019
Fully Permitted
Feb 01, 2021
Certificate of Occupancy
Mar 03, 2021
Building Completion (HPD)