Duration

Total Duration:13.9 years
Start Date:Jan 2008
End Date:Dec 2021

Identifiers

Project ID:63763
Building ID:984726

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
200820102012201420162018202020222024ActualOfficialCONEY ISLAND PHASE 1 (L&M)2926 WEST 19 STREET(Boro: 3, Block: 7060, Lot: 7501)Brooklyn13.9yrs3.4yrs

Timeline Events (12)

Jan 11, 2008
⚠️ City Map Amendment + Zoning Text Amendment (Contemplated) + Zoning Map Amendment (Contemplated) + Acquisition City Property (Contemplated) + Udaap Designation (Contemplated) + Disposition City Owned Property (Contemplated) [P2009K0065] Positive Declaration (EIS Required)
Jan 11, 2008
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment [P2009K0185] Positive Declaration (EIS Required)
Jan 16, 2009
Zoning Text Amendment [P2009K0264] EAS Date
Feb 28, 2018
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Other Discretionary Permit [NO_ZAP_18HPD084K] Earliest EAS Work (Site Survey)
Mar 09, 2018
Earliest DOB Filing
Apr 20, 2018
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Other Discretionary Permit [NO_ZAP_18HPD084K] Lead Agency Letter
May 10, 2018
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Other Discretionary Permit [NO_ZAP_18HPD084K] EAS Date
May 17, 2018
✅ Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Other Discretionary Permit [NO_ZAP_18HPD084K] Negative Declaration
Jun 29, 2018
HPD Financing ("Project Start")
Dec 18, 2018
Fully Permitted
Oct 28, 2021
Certificate of Occupancy
Dec 06, 2021
Building Completion (HPD)