CUCS. 302-314 W 127TH STREET. KELLY HOTEL
310 WEST 127 STREET (Boro: 1, Block: 1953, Lot: 36)
Manhattan
Duration
Total Duration:7.5 years
Start Date:Jun 2013
End Date:Dec 2020
RFP Information
NYC Supportive Housing RFQ
Identifiers
Project ID:63367
Building ID:982777
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (11)
Jun 25, 2013
RFP Release: NYC Supportive Housing RFQ
Mar 19, 2014
✅ RFP Designation: NYC Supportive Housing RFQ
Feb 01, 2016
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2015M0320] Earliest EAS Work (Phase I ESA)
Jul 11, 2017
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2015M0320] Lead Agency Letter
Oct 12, 2017
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2015M0320] EAS Date
Oct 13, 2017
✅ Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2015M0320] Negative Declaration
Feb 15, 2018
Earliest DOB Filing
Jun 26, 2018
HPD Financing ("Project Start")
Mar 18, 2019
Fully Permitted
Dec 29, 2020
Certificate of Occupancy
Dec 29, 2020
Building Completion (HPD)