HUNTERS POINT SOUTH PARCEL C -NORTH TOWER
52-03 CENTER BOULEVARD (Boro: 4, Block: 6, Lot: 7504)
Queens
Duration
Total Duration:14.6 years
Start Date:Apr 2007
End Date:Nov 2021
RFP Information
Hunter's Point South Parcel C RFP
Identifiers
Project ID:61931
Building ID:981672
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (11)
Apr 11, 2007
Zoning Map Amendment + Zoning Text Amendment (Contemplated) + City Map Amendment + Disposition City Owned Property + Acquisition City Property (Contemplated) + Site Selection Public Facility [NO_ZAP_07DME023Q] Lead Agency Letter
Oct 05, 2007
City Map Amendment + Zoning Map Amendment + Zoning Text Amendment + Acquisition City Property + Disposition City Owned Property + Udaap Designation [P2008Q0279] EAS Date
Oct 12, 2007
City Map Amendment + Zoning Map Amendment + Zoning Text Amendment + Acquisition City Property + Disposition City Owned Property + Udaap Designation [P2008Q0279] Lead Agency Letter
Oct 12, 2007
⚠️ City Map Amendment + Zoning Map Amendment + Zoning Text Amendment + Acquisition City Property + Disposition City Owned Property + Udaap Designation [P2008Q0279] Positive Declaration (EIS Required)
Apr 30, 2013
RFP Release: Hunter's Point South Parcel C RFP
Dec 05, 2013
✅ RFP Designation: Hunter's Point South Parcel C RFP
Oct 23, 2017
Earliest DOB Filing
Dec 26, 2018
HPD Financing ("Project Start")
May 24, 2019
Fully Permitted
Nov 29, 2021
Building Completion (HPD)
Nov 29, 2021
Certificate of Occupancy