LA CENTRAL/BRONXCHESTER - BUILDINGS A & B
600 BERGEN AVENUE (Boro: 2, Block: 2361, Lot: 7501)
Bronx
Duration
Total Duration:21.9 years
Start Date:Jan 2002
End Date:Dec 2023
RFP Information
Bronxchester RFP
Identifiers
Project ID:51302
Building ID:979324
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (15)
Jan 01, 2002
Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Special Permit Cpc [NO_ZAP_06DME005X] Earliest EAS Work (Phase I ESA)
Oct 31, 2005
Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Special Permit Cpc [NO_ZAP_06DME005X] EAS Date
Nov 01, 2005
Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Special Permit Cpc [NO_ZAP_06DME005X] Lead Agency Letter
Nov 01, 2005
⚠️ Disposition City Owned Property + Zoning Map Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc + Zoning Special Permit Cpc [NO_ZAP_06DME005X] Positive Declaration (EIS Required)
Mar 29, 2013
RFP Release: Bronxchester RFP
Dec 21, 2013
✅ RFP Designation: Bronxchester RFP
Jul 24, 2014
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2013X0354] Earliest EAS Work (Phase I ESA)
Jun 30, 2015
Earliest DOB Filing
Oct 05, 2015
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2013X0354] Lead Agency Letter
Oct 05, 2015
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2013X0354] EAS Date
Oct 05, 2015
⚠️ Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2013X0354] Positive Declaration (EIS Required)
Dec 28, 2017
HPD Financing ("Project Start")
Jun 15, 2018
Fully Permitted
Apr 05, 2021
Certificate of Occupancy
Dec 05, 2023
Building Completion (HPD)