ARKER.40 DEBEVOISE STREET
40 DEBEVOISE STREET (Boro: 3, Block: 3127, Lot: 7501)
Brooklyn
Duration
Total Duration:3.8 years
Start Date:Sep 2017
End Date:Jun 2021
Identifiers
Project ID:65543
Building ID:978829
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Sep 01, 2017
Hpd Construction Financing [NO_ZAP_18HPD057K] Earliest EAS Work (Phase I ESA)
Nov 21, 2017
Earliest DOB Filing
Mar 09, 2018
Hpd Construction Financing [NO_ZAP_18HPD057K] Lead Agency Letter
Mar 23, 2018
Hpd Construction Financing [NO_ZAP_18HPD057K] EAS Date
Mar 29, 2018
✅ Hpd Construction Financing [NO_ZAP_18HPD057K] Negative Declaration
May 23, 2018
HPD Financing ("Project Start")
May 20, 2021
Fully Permitted
Jun 15, 2021
Building Completion (HPD)
Jun 15, 2021
Certificate of Occupancy