COMPASS 3
1560 BOONE AVENUE (Boro: 2, Block: 3014, Lot: 7502)
Bronx
Duration
Total Duration:11.1 years
Start Date:Jan 2010
End Date:Feb 2021
Identifiers
Project ID:65213
Building ID:977584
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (14)
Jan 13, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property [P2010X0193] EAS Date
Jan 13, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Hpd Hdc Program Funding (Contemplated) [P2011X0142] EAS Date
Jan 13, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [P2011X0180] EAS Date
Jan 25, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property [P2010X0193] Lead Agency Letter
Jan 25, 2010
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property [P2010X0193] Positive Declaration (EIS Required)
Jan 25, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Hpd Hdc Program Funding (Contemplated) [P2011X0142] Lead Agency Letter
Jan 25, 2010
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Hpd Hdc Program Funding (Contemplated) [P2011X0142] Positive Declaration (EIS Required)
Jan 25, 2010
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [P2011X0180] Lead Agency Letter
Jan 25, 2010
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [P2011X0180] Positive Declaration (EIS Required)
Jul 14, 2017
Earliest DOB Filing
Dec 28, 2017
HPD Financing ("Project Start")
Mar 26, 2018
Fully Permitted
Feb 20, 2020
Certificate of Occupancy
Feb 22, 2021
Building Completion (HPD)