ROCHESTER SUYDAM PHASE 1

329 RALPH AVENUE (Boro: 3, Block: 1556, Lot: 7)
Brooklyn

Duration

Total Duration:18.9 years
Start Date:Aug 2005
End Date:Jul 2024

RFP Information

New Foundations Homeownership Program Round III RFP

Identifiers

Project ID:44223
Building ID:977564
Data Quality Note
19-36 (Fair)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20052007200920112013201520172019202120232025ActualOfficial
ROCHESTER SUYDAM PHASE 1329 RALPH AVENUE(Boro: 3, Block: 1556, Lot: 7)Brooklyn18.9yrs3.1yrs

Timeline Events (14)

Aug 29, 2005
RFP Release: New Foundations Homeownership Program Round III RFP
Mar 28, 2007
Zoning Map Amendment + Zoning Text Amendment [P2007K0317] Earliest EAS Work (Noise Monitoring)
May 04, 2007
Zoning Map Amendment + Zoning Text Amendment [P2007K0317] Lead Agency Letter
May 04, 2007
Zoning Map Amendment + Zoning Text Amendment [P2007K0317] EAS Date
May 07, 2007
✅ Zoning Map Amendment + Zoning Text Amendment [P2007K0317] Negative Declaration
May 22, 2015
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing [NO_ZAP_16HPD054K] Earliest EAS Work (Phase I ESA)
Feb 09, 2016
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing [NO_ZAP_16HPD054K] Lead Agency Letter
Mar 31, 2016
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing [NO_ZAP_16HPD054K] EAS Date
Mar 31, 2016
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing [NO_ZAP_16HPD054K] Negative Declaration
Feb 22, 2019
✅ Udaap Designation + Disposition City Owned Property [P2017K0240] Negative Declaration
May 05, 2020
Earliest DOB Filing
Jun 30, 2021
HPD Financing ("Project Start")
Aug 20, 2021
Fully Permitted
Jul 24, 2024
Building Completion (HPD)