DEKALB COMMONS
648 DEKALB AVENUE (Boro: 3, Block: 1779, Lot: 22)
Brooklyn
Duration
Total Duration:6.1 years
Start Date:Jul 2017
End Date:Aug 2023
Identifiers
Project ID:64728
Building ID:976970
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (7)
Jul 01, 2017
Udaap Designation + Disposition City Owned Property [P2017K0364] Earliest EAS Work (Phase I ESA)
Oct 05, 2018
Udaap Designation + Disposition City Owned Property [P2017K0364] Lead Agency Letter
May 23, 2019
Udaap Designation + Disposition City Owned Property [P2017K0364] EAS Date
Jun 04, 2019
⚠️ Udaap Designation + Disposition City Owned Property [P2017K0364] Positive Declaration (EIS Required)
Apr 29, 2020
Earliest DOB Filing
Jun 22, 2023
HPD Financing ("Project Start")
Aug 14, 2023
Fully Permitted