142-150 SOUTH PORTLAND
142-150 SOUTH PORTLAND AVENUE (Boro: 3, Block: 2003, Lot: 37)
Brooklyn
Duration
Total Duration:8.2 years
Start Date:Apr 2017
End Date:Jun 2025
Identifiers
Project ID:64608
Building ID:976722
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Apr 01, 2017
Zoning Map Amendment + Zoning Text Amendment [P2016K0180] Earliest EAS Work (Phase I Environmental Site Assessment)
Dec 29, 2017
Zoning Map Amendment + Zoning Text Amendment [P2016K0180] Lead Agency Letter
Dec 29, 2017
Zoning Map Amendment + Zoning Text Amendment [P2016K0180] EAS Date
Jan 02, 2018
✅ Zoning Map Amendment + Zoning Text Amendment [P2016K0180] Negative Declaration
May 15, 2019
Earliest DOB Filing
Sep 23, 2021
HPD Financing ("Project Start")
Mar 31, 2022
Fully Permitted
Feb 28, 2024
Certificate of Occupancy
Jun 26, 2025
Building Completion (HPD)