BELMONT COVE

656 EAST 176 STREET (Boro: 2, Block: 2945, Lot: 34)
Bronx

Duration

Total Duration:6.7 years
Start Date:Sep 2018
End Date:Jun 2025

Identifiers

Project ID:60031
Building ID:976441

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20182019202020212022202320242025ActualOfficialBELMONT COVE656 EAST 176 STREET(Boro: 2, Block: 2945, Lot: 34)Bronx6.7yrs3.0yrs

Timeline Events (6)

Sep 19, 2018
✅ Zoning Map Amendment + Disposition City Owned Property + Zoning Text Amendment [P2016X0079] Negative Declaration
Mar 19, 2019
Earliest DOB Filing
Jun 29, 2022
HPD Financing ("Project Start")
Nov 09, 2022
Fully Permitted
Jun 17, 2025
Building Completion (HPD)
Jun 17, 2025
Certificate of Occupancy