CAMBA. 210-214 HEGEMAN AVE
212 HEGEMAN AVENUE (Boro: 3, Block: 3639, Lot: 35)
Brooklyn
Duration
Total Duration:7.3 years
Start Date:Jun 2013
End Date:Sep 2020
RFP Information
NYC Supportive Housing RFQ
Identifiers
Project ID:62289
Building ID:976044
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (11)
Jun 25, 2013
RFP Release: NYC Supportive Housing RFQ
Mar 19, 2014
✅ RFP Designation: NYC Supportive Housing RFQ
Apr 20, 2016
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Other Discretionary Permit + Hpd Construction Financing (Contemplated) [P2016K0273] Earliest EAS Work (Noise Monitoring)
Oct 13, 2016
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Other Discretionary Permit + Hpd Construction Financing (Contemplated) [P2016K0273] Lead Agency Letter
Nov 14, 2016
Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Other Discretionary Permit + Hpd Construction Financing (Contemplated) [P2016K0273] EAS Date
Nov 14, 2016
✅ Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc + Other Discretionary Permit + Hpd Construction Financing (Contemplated) [P2016K0273] Negative Declaration
Jan 24, 2017
Earliest DOB Filing
Jan 22, 2018
HPD Financing ("Project Start")
Sep 20, 2018
Fully Permitted
Sep 30, 2020
Certificate of Occupancy
Sep 30, 2020
Building Completion (HPD)