LINWOOD PARK APARTMENTS
3002 ATLANTIC AVENUE (Boro: 3, Block: 3971, Lot: 19)
Brooklyn
Duration
Total Duration:5.1 years
Start Date:Oct 2015
End Date:Nov 2020
Identifiers
Project ID:63769
Building ID:976030
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Oct 01, 2015
Hpd Construction Financing [NO_ZAP_18HPD037K] Earliest EAS Work (Phase I Environmental Site Assessment)
Jun 29, 2017
Earliest DOB Filing
Apr 13, 2018
Hpd Construction Financing [NO_ZAP_18HPD037K] Lead Agency Letter
May 14, 2018
Hpd Construction Financing [NO_ZAP_18HPD037K] EAS Date
May 25, 2018
✅ Hpd Construction Financing [NO_ZAP_18HPD037K] Negative Declaration
Jun 28, 2018
HPD Financing ("Project Start")
Jul 31, 2018
Fully Permitted
May 27, 2020
Certificate of Occupancy
Nov 04, 2020
Building Completion (HPD)