EBENEZER PLAZA PHASE 1A

94 NEW LOTS AVENUE (Boro: 3, Block: 3862, Lot: 7501)
Brooklyn

Duration

Total Duration:16.2 years
Start Date:Sep 2005
End Date:Nov 2021

Identifiers

Project ID:61612
Building ID:975696
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20052007200920112013201520172019202120232025ActualOfficial
EBENEZER PLAZA PHASE 1A94 NEW LOTS AVENUE(Boro: 3, Block: 3862, Lot: 7501)Brooklyn16.2yrs2.9yrs

Timeline Events (10)

Sep 26, 2005
Zoning Map Amendment [P2006K0223] Lead Agency Letter
Nov 03, 2015
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] Earliest EAS Work (Phase I ESA)
Feb 27, 2017
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] Lead Agency Letter
Mar 17, 2017
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] EAS Date
Mar 20, 2017
✅ Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0526] Negative Declaration
Jun 22, 2018
HPD Financing ("Project Start")
Aug 31, 2018
Earliest DOB Filing
Aug 08, 2019
Fully Permitted
May 25, 2021
Building Completion (HPD)
Nov 29, 2021
Certificate of Occupancy