BFC. 140 ESSEX ST. ESSEX CROSSING SITE 8
140 ESSEX STREET (Boro: 1, Block: 354, Lot: 1)
Manhattan
Duration
Total Duration:8.3 years
Start Date:Sep 2011
End Date:Dec 2019
RFP Information
Seward Park RFP
Identifiers
Project ID:61728
Building ID:975686
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Sep 07, 2011
⚠️ Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property + Zoning Map Amendment [P2014M0451] Positive Declaration (EIS Required)
Sep 07, 2011
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + City Map Amendment [P2012M0292] Positive Declaration (EIS Required)
Jan 09, 2013
RFP Release: Seward Park RFP
Sep 18, 2013
✅ RFP Designation: Seward Park RFP
Feb 27, 2017
Earliest DOB Filing
Nov 01, 2017
HPD Financing ("Project Start")
Aug 06, 2018
Fully Permitted
Oct 03, 2019
Certificate of Occupancy
Dec 11, 2019
Building Completion (HPD)