425 GRAND CONCOURSE (Boro: 2, Block: 2346, Lot: 7501)
Bronx

Duration

Total Duration:6.9 years
Start Date:Jun 2015
End Date:May 2022

RFP Information

425 Grand Concourse RFP

Identifiers

Project ID:51582
Building ID:975396

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficial425 GRAND CONCOURSE425 GRAND CONCOURSE(Boro: 2, Block: 2346, Lot: 7501)Bronx6.9yrs2.4yrs

Timeline Events (12)

Jun 29, 2015
RFP Release: 425 Grand Concourse RFP
Apr 28, 2016
✅ RFP Designation: 425 Grand Concourse RFP
Sep 23, 2016
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment [P2016X0435] Earliest EAS Work (Phase I ESA)
Apr 14, 2017
Earliest DOB Filing
Jul 14, 2017
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment [P2016X0435] Lead Agency Letter
Aug 02, 2017
Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment [P2016X0435] EAS Date
Aug 03, 2017
✅ Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment [P2016X0435] Negative Declaration
Dec 10, 2019
Other Discretionary Permit [2020X0347] Lead Agency Letter
Dec 20, 2019
HPD Financing ("Project Start")
Feb 11, 2020
Fully Permitted
May 16, 2022
Building Completion (HPD)
May 16, 2022
Certificate of Occupancy