Duration
Total Duration:8.1 years
Start Date:Oct 2015
End Date:Nov 2023
RFP Information
Lower Concourse North RFEI
Identifiers
Project ID:63772
Building ID:975365
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (12)
Oct 01, 2015
Zoning Map Amendment + Zoning Text Amendment + Zoning Text Amendment + Zoning Text Amendment + Disposition City Owned Property + Zoning Special Permit Cpc [2021X0277] Earliest EAS Work (Phase I ESA)
Jul 13, 2016
RFP Release: Lower Concourse North RFEI
Nov 03, 2016
Zoning Map Amendment + Zoning Text Amendment + Zoning Text Amendment + Zoning Text Amendment + Disposition City Owned Property + Zoning Special Permit Cpc [2021X0277] Lead Agency Letter
Nov 03, 2016
Zoning Map Amendment + Zoning Text Amendment + Zoning Text Amendment + Zoning Text Amendment + Disposition City Owned Property + Zoning Special Permit Cpc [2021X0277] EAS Date
Nov 03, 2016
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Text Amendment + Zoning Text Amendment + Disposition City Owned Property + Zoning Special Permit Cpc [2021X0277] Positive Declaration (EIS Required)
Dec 02, 2016
Disposition City Owned Property + Zoning Special Permit Cpc + Zoning Map Amendment + Zoning Text Amendment [P2016X0409] EAS Date
Feb 12, 2019
Earliest DOB Filing
Jun 12, 2019
✅ Udaap Designation [P2018X0177] Negative Declaration
Dec 29, 2020
HPD Financing ("Project Start")
May 12, 2021
Fully Permitted
Nov 02, 2023
Building Completion (HPD)
Nov 02, 2023
Certificate of Occupancy