WESTCHESTER MEWS
2035 NEWBOLD AVENUE (Boro: 2, Block: 3805, Lot: 7502)
Bronx
Duration
Total Duration:3.7 years
Start Date:Jan 2017
End Date:Sep 2020
Identifiers
Project ID:44431
Building ID:974694
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (4)
Jan 20, 2017
Earliest DOB Filing
Jun 27, 2017
Project Start (HPD)
Jun 30, 2020
Certificate of Occupancy
Sep 25, 2020
Building Completion (HPD)