THE GRAND

220 EAST 178 STREET (Boro: 2, Block: 2810, Lot: 17)
Bronx

Duration

Total Duration:6.6 years
Start Date:Dec 2015
End Date:Jul 2022

Identifiers

Project ID:62211
Building ID:974228

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficialTHE GRAND220 EAST 178 STREET(Boro: 2, Block: 2810, Lot: 17)Bronx6.6yrs4.8yrs

Timeline Events (9)

Dec 01, 2015
Hpd Construction Financing + Funding Programs [NO_ZAP_17HPD059X] Earliest EAS Work (Phase I ESA)
Aug 19, 2016
Earliest DOB Filing
Jun 19, 2017
Hpd Construction Financing + Funding Programs [NO_ZAP_17HPD059X] EAS Date
Jun 21, 2017
Hpd Construction Financing + Funding Programs [NO_ZAP_17HPD059X] Lead Agency Letter
Jun 21, 2017
✅ Hpd Construction Financing + Funding Programs [NO_ZAP_17HPD059X] Negative Declaration
Sep 28, 2017
HPD Financing ("Project Start")
Apr 13, 2018
Fully Permitted
Jul 20, 2022
Building Completion (HPD)
Jul 20, 2022
Certificate of Occupancy