888 FOUNTAIN AVENUE BUILDING A2

911 ERSKINE STREET (Boro: 3, Block: 4586, Lot: 7501)
Brooklyn

Duration

Total Duration:14.4 years
Start Date:Jan 2006
End Date:May 2020

Identifiers

Project ID:60779
Building ID:974205

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2006200820102012201420162018202020222024ActualOfficial888 FOUNTAIN AVENUE BUILDING A2911 ERSKINE STREET(Boro: 3, Block: 4586, Lot: 7501)Brooklyn14.4yrs3.4yrs

Timeline Events (24)

Jan 01, 2006
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [P2007K0196] Earliest EAS Work (Field surveys and data collection)
Jan 01, 2006
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2008K0074] Earliest EAS Work (Field Surveys and Data Collection)
Jan 01, 2006
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2018K0122] Earliest EAS Work (Field surveys and data collection)
Mar 01, 2006
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [2022K0289] Earliest EAS Work (Soil Borings and Site Investigation)
Sep 01, 2006
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2009K0050] Earliest EAS Work (Field surveys and data collection)
Feb 01, 2007
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [2022K0289] Lead Agency Letter
Feb 01, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [2022K0289] Positive Declaration (EIS Required)
Feb 01, 2007
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2009K0050] Lead Agency Letter
Feb 06, 2007
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [P2007K0196] EAS Date
Feb 06, 2007
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2008K0074] EAS Date
Feb 06, 2007
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2009K0050] EAS Date
Feb 06, 2007
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2018K0122] EAS Date
Feb 15, 2007
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [P2007K0196] Lead Agency Letter
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc [P2007K0196] Positive Declaration (EIS Required)
Feb 15, 2007
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2008K0074] Lead Agency Letter
Feb 15, 2007
⚠️ City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2008K0074] Positive Declaration (EIS Required)
Feb 15, 2007
⚠️ City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2009K0050] Positive Declaration (EIS Required)
Feb 15, 2007
City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2018K0122] Lead Agency Letter
Feb 15, 2007
⚠️ City Map Amendment + Zoning Map Amendment + Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property [P2018K0122] Positive Declaration (EIS Required)
Aug 26, 2016
Earliest DOB Filing
Dec 22, 2016
HPD Financing ("Project Start")
Jul 10, 2017
Fully Permitted
May 29, 2020
Certificate of Occupancy
May 29, 2020
Building Completion (HPD)